With 35 km of pipelines to renew between Saint-Romain-Le-Noble, Valence d’Agen and Caumont, the Valence d’Agen project guarantees the integrity and security of gas infrastructures in Occitanie and Nouvelle-Aquitaine. It fits perfectly into the territories’ energy transition, guaranteeing the transport of more secure and more sustainable gas supplies.

Gas transportValence d'Agen

2021-2028

With 35 km of pipelines to renew between Saint-Romain-Le-Noble, Valence d’Agen and Caumont, the Valence d’Agen project guarantees the integrity and security of gas infrastructures in Occitanie and Nouvelle-Aquitaine. It fits perfectly into the territories’ energy transition, guaranteeing the transport of more secure and more sustainable gas supplies.

Goals

  • Replacing 35 km of pipelines in Occitanie and Nouvelle-Aquitaine
  • Bringing a pipeline that is more than 70 years old up to current standards
  • Connection of the Garonne Biogaz biomethane injection unit to the grid
  • Securing gas supplies to local public and industrial distribution networks

Schedule

  • 2021 - 2024 : Research

  • September 2024 : Submission of the DACE (Application for Authorisation to Build and Operate)

  • September 2024 - July 2026: Administrative review

  • Autumn 2025: Public enquiry

  • Summer 2026: Orders obtained

  • 2026-2027: Completion of the construction work

  • 2028: Commissioning and abandonment of old pipelines