With 35 km of pipelines to renew between Saint-Romain-Le-Noble, Valence d’Agen and Caumont, the Valence d’Agen project guarantees the integrity and security of gas infrastructures in Occitanie and Nouvelle-Aquitaine. It fits perfectly into the territories’ energy transition, guaranteeing the transport of more secure and more sustainable gas supplies.
2021-2028
With 35 km of pipelines to renew between Saint-Romain-Le-Noble, Valence d’Agen and Caumont, the Valence d’Agen project guarantees the integrity and security of gas infrastructures in Occitanie and Nouvelle-Aquitaine. It fits perfectly into the territories’ energy transition, guaranteeing the transport of more secure and more sustainable gas supplies.
2021 - 2024 : Research
September 2024 : Submission of the DACE (Application for Authorisation to Build and Operate)
September 2024 - July 2026: Administrative review
Autumn 2025: Public enquiry
Summer 2026: Orders obtained
2026-2027: Completion of the construction work
2028: Commissioning and abandonment of old pipelines