Commissioned in 1974, the pipeline connecting the municipalities of Narbonne (11) and Claira (66) must be replaced to guarantee the security of the territories' energy supply.
2024-2029
Built in 1974, the pipeline connecting the municipalities of Narbonne (11) and Claira (66) is undergoing a renewal process to guarantee the long-term continuity and security of regional natural gas supplies for both public and industrial consumers.
2024 - 2025: Studies
January 2026: Filing of the DACE (Demande d'Autorisation de Construire et d'Exploiter - Application for Authorization to Construct and Operate)
January 2027: Public inquiry
July 2027: Obtaining of prefectural orders
September 2027: Start of construction works
Late 2028 - Early 2029: Commissioning and decommissioning of the old pipeline