Commissioned in 1974, the pipeline connecting the municipalities of Narbonne (11) and Claira (66) must be replaced to guarantee the security of the territories' energy supply.

Gas transportNarbonne-Claira

2024-2029

Built in 1974, the pipeline connecting the municipalities of Narbonne (11) and Claira (66) is undergoing a renewal process to guarantee the long-term continuity and security of regional natural gas supplies for both public and industrial consumers.

Goals

  • Replacement of 52 km of pipelines and creation of a new 57.9 km pipeline
  • Bringing a pipeline over 50 years old up to modern standards
  • Securing the gas supply for local public distribution networks and industrial consumers

Schedule

  • 2024 - 2025: Studies

  • January 2026: Filing of the DACE (Demande d'Autorisation de Construire et d'Exploiter - Application for Authorization to Construct and Operate)

  • January 2027: Public inquiry

  • July 2027: Obtaining of prefectural orders

  • September 2027: Start of construction works

  • Late 2028 - Early 2029: Commissioning and decommissioning of the old pipeline