Narbonne-Claira

Transport du gaz

Narbonne-Claira

2024-2029

Commissioned in 1974, the pipeline connecting the municipalities of Narbonne (11) and Claira (66) must be replaced to guarantee the security of the territories' energy supply.

Narbonne-Claira

Objectifs du projet

Security

Replacement of 52 km of pipelines and creation of a new 57.9 km pipeline

Network Modernization

Bringing a pipeline over 50 years old up to modern standards

Operational

Securing the gas supply for local public distribution networks and industrial consumers

Narbonne-Claira: A Project Serving the Territories

Located between the communes of Narbonne and Claira, this project addresses the need to modernize and secure our gas transmission infrastructure within the Aude and Pyrénées-Orientales departments.

With pipelines dating back more than 50 years, Teréga must renew its network to comply with current regulatory and technical requirements.

Key figures

52 km

of pipelines decommissioned

57.9 km

of pipeline with a nominal diameter (DN) of 250 mm

1.3 km

of pipeline with a DN of 80

4

shut-off station to adapt

66.2 bars

Maximum Operating Pressure (MOP)

Narbonne-Claira schedule

Narbonne-Claira schedule

Prior public consultation

The alignment of the PLU (Plan Local d'Urbanisme - Local Urban Plan) is required for the natural gas transmission pipeline construction project ("Narbonne-Claira" project) carried out by Teréga.

The route of the future pipeline crosses "classified wooded areas" within the municipalities of Narbonne (11) and Sigean (11). To ensure the project complies with the PLU, it is necessary to modify the zoning of the classified wooded area along the future facility.

This compliance procedure is subject to a public consultation under the Urban Planning Code. It will take place from August 24, 2026, to September 7, 2026.

Organized under the Urban Planning Code (art. L103-2), this consultation aims to:

  • Inform the public of the PLU compliance project.

  • Allow the population, particularly local residents, to review its specifications.

  • Allow any interested person to submit their observations.

Information media available to you

A consultation file will be available to the public throughout the process:

To learn more about the project, you can read the explanatory notices and the PLU compliance files available below:

Means of expression

If you wish to ask a question, share an opinion, or make a proposal, you can contribute from August 24, 2026, to September 7, 2026:

  • By email: johan.gaillet@terega.fr, Project Manager

  • Via paper registry made available to the public in the town halls of Narbonne and Sigean.

Project contact

Project contact

johan.gaillet@terega.fr, Project Manager